-

Welcome to the 
WESTERN LOCOMOTIVE ASSOCIATION

Owners and operators of two CLASS 52 DIESEL HYDRAULIC LOCOMOTIVES on the 
Severn Valley Railway.

D1013 Western Ranger - Bogie Overhaul Appeal

The Western Locomotive Association is making good steady progress with the overhaul of D1013 and over the last few years the locomotive has benefited from literally thousands of hours of volunteer help, which so far has included a full electrical re-wire, component overhauls including pre-heaters, fuel pumps, cooler groups, cooling fans, cardan shafts, exhausters, air receivers, cab desk rebuilds, internal paintwork etc, and not to mention current on-going work to overhaul its two massive 65 Litre V12 engines.
Why so much work ?
D1013 was built and introduced into service in December 1962, and subsequently clocked up 1.32 million miles before withdrawal in February 1977. Its last overhaul was with British Rail (Western Region) over 45 years ago!

Of course general maintenance work has been carried out since the locomotive was withdrawn from mainline running as the locomotive has spent most of its time in preservation, operating primarily on the Severn Valley Railway. However, many major components were in need of major overhaul and the electrical wiring was getting to the point where it could become a potential fire risk. In the end, with safety being of paramount importance, the best and only option was to withdraw the locomotive from traffic and embark on its current major overhaul.

To what standard is the work being done ?
Once withdrawn from traffic, it was agreed that any work would be at least to the standard or better than BR would have achieved. This means that everything is overhauled in accordance with original equipment manufacturer's (OEM) specifications and requirements, using materials that are equivalent or better. Where necessary, specialist items (such as cardan shafts and brake valves) are returned to approved companies where the work can conform to safety standards, with full certification. In effect, all the work is being done to "mainline" standard and as if the locomotive were to return to the mainline hauling passenger trains over Network Rail. The philosophy is that "if the locomotive is fit for the mainline", then it  is fit to run on privately preserved lines such as the Severn Valley.

What other work is required ?
Work carried out over the past 10 years has been above the solebar - above the bogie wheel sets. Consideration now has to be given to the bogies themselves as it is a fact that the locomotive has not been lifted for over 45 years! Experience gained by the Diesel Traction Group (DTG) with their locomotive D1015 Western Champion, and also with some experience gained by the WLA in lifting D1062 Western Courier, has indicated that D1013 will need a full bogie overhaul if it is to gain a new lease of life for the next 150,000 miles over the next 40 years or so. This work includes lifting the locomotive off its bogies for an initial assessment, prior to a complete strip down, clean, overhaul, repair and reassembly, A major part of this work will require the wheel sets to be re-tyred as currently they are virtually life expired on minimum thickness safety levels.

How are we going to do a bogie overhaul ?
Whilst the WLA has some experience with bogie work, much of this will need to be outsourced to specialist engineering companies to make sure the work complies with safety standards and meets the specifications that were in place in BR days. The WLA is fortunate to be able to liaise with the DTG who have restored three bogies to mainline standard for D1015. A process of adopting appropriate paperwork is underway which will eventually lead to a specification for the overhaul of both bogies. This will include the strip down, shot-blasting and repairs to the bogie frames, overhaul of the lateral dampers, new thrust pads, springs and overhaul of the final drives, whilst the wheel sets are re-tyred. Once the specifications have been drawn up for each part of the overhaul, the work will be placed out to tender, to gain costings and a budget.

So how much will a bogie overhaul likely cost ?
At the  present time, it is not known exactly how much but we do know that a re-tyre will cost around £20k per bogie, so £40k to start off with. It is anticipated that such a project is going to cost in the region of £200k but this figure will be clarified once items go out to tender.

How will the bogie project be funded ?
Clearly, this project is a massive undertaking for any volunteer group and therefore, in addition to volunteer "hands-on" help, the WLA will need to seek help from private donations, sponsorship and will need to apply for funding from the Heritage Lottery Fund (HLF).

If you would like to help out with this project in any way, whether it be "hands-on" help, engineering advice, sponsorship,donations etc, please contact us 

To donate now to D1013's bogie overhaul appeal, please use the DONATE button below, and please remember to sign up for Gift Aid if you don't already do so. It does not matter how large or small your donation as every little will help to what we believe is a very worthy cause.

What will the benefits be ?
A fully working locomotive that has had thousands of hours of volunteer labour spent on it, able to return to the Severn Valley Railway for the enjoyment of many thousands of people who visit for operating days, gala weekends and special events, plus the option of visiting other heritage railways and depot open days throughout the UK.

To donate, please use the DONATE button below, and please remember to Gift Aid it if you don't already.

If you prefer to send a cheque then please post to D1013 Bogie Appeal, 25 Foxhills Close, Appleton, Warrington, Cheshire, WA4 5DH

THANK YOU!